Dams in Developing
Nations
Introduction
| Brazil - Tucuruí Dam | China
-Three Gorges Dam | Philippines - San Marcelino
Dam | Links
- Introduction
- Definition: structure built across a stream, river, or estuary
to retain water (or debris)
- History
- Dams have been around for ~5,000 years
- Domestic and agricultural usage
- Advances in technology coincides with population
increas
- 19th & 20th Centuries
- Increased electricity demand = larger dams
- Increased population = need for flood protection
- Dams now serve various purposes
- Current uses of Dams
- Hydroelectric power
- Flood control
- Water Storage
- Tailings / Mining Dams
- Types of Dams
- Arch Dams
- Curved - dependent upon arch action for its strength.
- Thinner and therefore require less material
- Good for sites that are narrow and have strong abutments.
- Buttress Dams
- Face (front) is held up by a series of supports.
- Have many forms - the face may be flat or curved.
- Gravity Dams
- Resist the horizontal thrust of the water entirely by
their own weight.
- Typically used to block streams through narrow gorges.
- Use a large amounts of concrete. This can be expensive.
- Many prefer its solid strength to arch or buttress dams.
- Embankment Dams
- Massive dams made of earth or rock.
- Rely on their weight to resist the flow of water
- Tailings Dams
- Tailings are waste material from the mining industry
- Must separate ore from rock
- Floatation method often used
- Waste is stored in tailings dams
- Three types of embankments
- downstream,
- upstream
- and centerline structures
- Type used is dependant upon many factors, including
- Upstream Design Tailings Dam
- Common
- Inexpensive
- Prone to failures
- Centerline Design Tailings Dam
- Mix of up and downstream design
- Cannot be used for water retention
- Downstream Design Tailings Dam
- Can hold more water
- More stable design
- Costs increase exponentially with height
- Other parts of a dam may include
- spillways, gates, or valves
- an intake structure conducting water to a power station
or to pipelines
- provision for evacuating silt carried into the reservoir
- means for permitting ships or fish to pass the dam.
- Forces that Act on a Dam
- Main forces
- force of the reservoir water (W)
- weight of concrete (C)
- both forces together
- The main force on an embankment dam is water (W).
- The weight of the dam is also a force,
- Other forces
- internal water pressure
- temperature variations in the concrete
- earthquake loads
- settlement of the foundation or abutments
- Case Studies: Brazil - Tucuruí Dam
- Climate:
- mostly tropical, but temperate in south
- Terrain:
- mostly flat to rolling lowlands in north; some plains,
hills, mountains, and narrow coastal belt
- Background
- 93% of Brazils energy comes from hydroelectric
- More than one million people have been displaced by
the construction of Brazils dams
- 34,000 km2 have been inundated by reservoirs
- Little effort has been made for alternative energy
- The Tucuruí Dam
- Part of a World Commission on Dams study on the subject
of the development effectiveness of large dams.
- Phase I 1975 to 1984
- Phase II began in 1988; first turbine scheduled
to be operational by December 2002
- Structural Type: Gravity dam
- Reservoir: 2,875 km2
- Length: 1,321 m
- Height: 77 m
- Function / usage: Hydroelectric dam
- Power: 8,000 mW
- Environment - current issues:
- deforestation in Amazon Basin destroys the habitat and
endangers a multitude of plant and animal species indigenous
to the area
- lucrative illegal wildlife trade
- land degradation and water pollution caused by improper
mining activities
- wetland degradation
- The Tocantins River
- located completely within the province of Eastern
Amazonia
- Flows into the Amazon river estuary
- Annual volume of 334km3
- Catchment area of 758,000 km2 (7.5% of the land
mass of Brazil)
- Contributes to a well-defined and stable climatic
regime across this region
- Socio-Economic Impact
- Severity of the impacts was far greater than initially
foreseen
- Population doubled in 10 years
- Mandatory relocation programs and economic migrations
- Massive layoffs after Phase I completion
- Compensation packages did not take into account cultural
and historical values
- Parakanã
- Group split up and relocated numerous times
- August 1986, threatened to block the Transamazon
Highway and employ terror tactics
- Parakanã Programme / Parakanã Indigenous
Reserve.
- Assimilate the group into mainstream culture
- Establishment of villages and maintaining their
traditional hunting and gathering activities
- Asurini
- Territory below the dam
- Affected by migrant workers and displaced people
- 1970s road built through 9 km of Asurini
land
- 1997 new power line contemplated
- Asurini resorted to the destruction of public infrastructure
- Road built, no power line, and no Asurini compensation
- Increase in:
- Malaria, schistosomiasis, etc,
- Industrial accidents,
- Alcoholism
- Sexually transmitted diseases and AIDS
- Infant mortality in the 1980s rates 6x that
of Pará State and 5x that of all of Brazil
- Effects on Ecosystems
- Initially, concern was towards the effect of the ecosystems
on the construction project
- Water Quality
- Low dissolved oxygen levels downstream
- Reduced flooding downstream = fertilization processes
- Increase in mosquitoes = increase in malaria
- Fisheries
- Initially anticipated a high mortality rate during
& after dam construction
- Actual rates much higher due to low D.O. & nutrient
levels
- Terrestrial Impacts
- Submersion of 2,850 km2 of land including large
areas of rainforest
- Wildlife reserves with permanent a wildlife study
group established (Operação Curupira)
- Bans on hunting and poaching
- Capture and release of some 280,000 animals.
- Total cost = US $30 million
- Case Studies: Three Gorges Dam - China
- Background
- Location: Sandouping, Yichang, Hubei province
- Structural Type: Gravity
- Height: 181 m
- Length: 2,150 meters
- Reservoir Capacity: 1.39 trillion cubic feet
- Function / usage: Hydroelectric dam
- Comparison between the Three Gorges Dam and the worlds
largest dams (reservoir capacity, in cubic feet)
- Yangtze River, China
- Background
- Construction phase: 1994 2009
- Functions: Flood control, power generation, improved
navigation
- Yangtze River, China
- Background
- About 20,000 people are working nearly round
the clock to complete the structure by 2009.
- The lake that will form behind Three Gorges
Dam will stretch for about 350 miles -- the distance
from San Francisco to Los Angeles.
- Three Gorges Dam reservoir will actually be
visible from the moon! Source: http://www.pbs.org/wgbh/buildingbig
- Socio-Economic Impact
- 600,000+ people have had to be resettled
- 13 cities, 140 towns, more than 1,600 villages,
and 300 factories will be submerged
- Est. 1.3 1.9 million will eventually
have to leave
- Supposedly there are no contractual agreements
with the resettlement authorities
- Loss of culture, way of life, etc.
- Archeological Impact
- 1,300 known cultural heritage sites affected
- Budget for excavations severely reduced
- Looting common
- Problems
- Over budget
- Coercion and violence have been used against
communities affected by dams
- Critics arrested or forced into exile
- No Dam Inundation plan
- Increased silt build-up
- Decreased nutrient levels downstream
- Case Studies: San Marcelino Dam - Philippines
- Climate: tropical marine
- northeast monsoon (November to April);
- southwest monsoon (May to October)
- Terrain:
- mostly mountains with narrow to extensive coastal lowlands
- Natural hazards:
- usually affected by 15 and struck by five to six cyclonic
storms per year;
- landslides;
- active volcanoes;
- destructive earthquakes;
- tsunamis
- Natural resources:
- timber, petroleum, nickel, cobalt, silver, gold, salt,
copper
- The San Marcelino tailings dam spill
- Dizon Copper-Silver Mines, Incorporated (DCSMI)
- Operations ceased in 1997
- Two mine tailings dams
- Bayarong
- Size: 122-hectare
- 47 million cubic meters of mine tailings
- Supposed to be able to withstand a 9.5 EQ
- Camalca silt & debris
- Catch Basin
- San Marcelino Dam - Philippines
- History
- 1991
- Mt. Pinatubo erupted, creates Lake Mapanuepe
(spillway weakened)
- 1998
- spillway damaged by the effects of a typhoon
- 1999
- Mines and Geosciences Bureau noticed some
seepages at and partial erosion of the tailings
dams spillway
- Recommended the following:
- installation of siphons and electrical pumps
- strengthening/preserving the remaining concrete
portion of the spillway approach
- opening of the previously constructed drain
tunnel
- Recommendations heeded
- 10 days of rain from Typhoons Chedeng and
Dodong proved recommendations not enough.
- New, more aggressive measures proposed
- 2002
- August 27 inspection reveals damage to
dams & spillways, leakage into Lake Mapanuepe
- September 5 the Department of Environment
and Natural Resources called the sudden burst
of the dams "unlikely"
- September 11 spillway collapses, flooding
low-lying villages with mine wastes and other
chemicals
- September 12 1000 people evacuated
- 2003
- DENR Order:
- short term emergency measures to prevent
the overtopping of the dam,
- do the necessary repairs in order to rehabilitate
the partially collapsed spillway,
and pay the appropriate mine wastes and tailings
fee and penalty for the unauthorized discharge
of mine wastes/tailings.
Introduction
| Brazil - Tucuruí Dam | China
-Three Gorges Dam | Philippines - San Marcelino
Dam | Links | top
|